Tuesday, April 12, 2011

April...

Work has been progressing quickly on-site and the shell of the new Sports Hall in now complete.  The defining feature of the metal roof and wall cladding has been completed, with the windows and curtain-walling currently being installed.  During the Easter holidays work will begin on the new courtyard and netball/tennis courts.


Looking towards the teaching wall in the first floor classrooms


Feature rooflight in the first floor classrooms


View inside the Sports Hall


Looking towards the main entrance from the first floor landing,
where a staircase is soon to arrive...